November 19, 2026
Avenida Azul has no paved shoulder. Its curves and steep road cuts give drivers short sight lines, and according to the Eldorado Community Improvement Association, a large number of pedestrians walk it anyway to get from one greenbelt trail to the next. Santa Fe County's capital improvement plan says the same thing more plainly: children and walkers "currently must walk on the high-traffic, paved County road to access greenbelt trails."
That stretch now has a construction window. In its November 2026 Vistas newsletter, ECIA reports that Santa Fe County plans to build a paved hike/bike trail along Avenida Azul between Avenida Vista Grande and Encantado in the first half of 2027. The design is close to done. Tonight, Thursday, November 19, county staff present it to residents over Zoom, so this evening is the easiest time to see where the path will run, and how it will cross the big arroyo, while those details can still be asked about.
Two trail-related gatherings fall on the same Thursday:
If you aren't on the e-blast list yet, you can sign up at eldoradosf.org. For questions before or after the meeting, the newsletter names Dan Anderson of Santa Fe County Public Works as the contact, at [email protected]. He is also listed as project manager on the county's own project report.
The county's August 2026 capital projects report lists the job as Project #7720, a new multi-use trail from Avenida Vista Grande to Encantado Loop covering 1.15 miles. At that point the design was 90% complete, with design-only completion projected for September 30, 2026.
The route follows from the way Eldorado was platted. ECIA explains that the Eldorado subdivision has no road rights-of-way. Instead, the county owns large tracts of land that are much wider than the paved roads running through them. The new trail will lie almost entirely within that county road tract, the same approach used for the county's other hike/bike trails in Eldorado. On the ground, the strip beside Avenida Azul is mostly public land already, and that shapes how wide the path can be and how far it can sit from traffic.
The arroyo crossing has changed the most. An earlier concept called for a bridge over the large arroyo where Azul meets the Gallina Park greenbelt. Current plans use low-water crossings instead, similar to the ones where Eldorado's other hike/bike trails cross greenbelts. If you already walk the existing paths, you have crossed that kind of design before. For a walker or cyclist, the Azul trail at the Gallina Park arroyo should feel much like the other greenbelt crossings in Eldorado, and the meeting is the place to see exactly how.
The trail also fills a missing link in the network. ECIA says it will connect two greenbelt trails, which is exactly the walk people now make on the road itself. The Greenbelts and Hike/Bike map shows the existing paths as blue "Multi-Use Trails" lines, and the gap along Azul is easy to spot.
The project has moved a step at a time. Each step lines up with a public record, which makes it easier to follow what is still ahead.
| When | What happened | Record |
|---|---|---|
| 2020 | ECIA's board asks the county to put the Azul trail on its infrastructure capital improvement plan after hearing many requests from homeowners | ECIA, Nov. 2026 |
| 2021 session | Legislature appropriates $130,000 to plan, design and construct a pedestrian and bicycle trail along Avenida Azul | HB 285, 2021 |
| November 2022 | ECIA reports the Azul project will move into design the following year | ECIA, Dec. 2022 |
| November 2023 | County records $130,000 in capital outlay received | ICIP FY2026–2030 |
| April 2024 | County issues RFP No. 2024-0219-PW/DK for engineering services on the Avenida Azul Multi-Use Trail | County RFP |
| 2025 session | State capital outlay chart lists $550,000 for "Avenida Azul Muti-Use Trail Construct" | HB 450, 2025 |
| August 2026 | Design 90% complete | County report |
| First half of 2027 | Planned construction | ECIA, Nov. 2026 |
The newsletter also explains the push toward 2027. ECIA writes that a recently passed law requires capital outlay funds to be spent or encumbered by the end of 2026, and that the County Public Works Department has worked hard to finalize the plan so the funding won't be lost. That deadline helps explain why the design going on screen tonight is close to final.
A comparable project already exists. In late 2022, ECIA's board voted to support the county's priority of using hike/bike funding to pave the 1.3-mile section of the Avenida de Compadres trail. The 1.15-mile Azul trail is a little shorter than that stretch.
The trail's maintenance arrangement will be familiar. Under the agreement between ECIA and the county, as ECIA's board described it in 2022, the county funds and installs the hike/bike trails, ECIA maintains them, and the county handles repair and replacement. ECIA's Hike/Bike Paths page puts the existing network at about 13 miles beside Eldorado's main roads, with ECIA staff responsible for upkeep. Motorized vehicles aren't allowed, and the speed limit is 10 mph. The Azul path would join those 13 miles under the same rules.
The trail also borders ECIA's greenbelts, which the association describes as member-owned land that it manages with erosion control and trail improvements. The Eldorado Trail Volunteers who meet at the Maintenance Barn this morning are part of that work. Eldorado has several overlapping authorities, and this trail involves the county, ECIA and the state at once. We covered that overlap from a homeowner's side in In Eldorado, the Address Doesn't Tell You Who Fixes the Road.
The county's planning document gives useful context for tonight's questions. The FY2026–2030 infrastructure capital improvement plan, filed with the state, estimates the Azul trail's total cost at $3 million. That includes $1.82 million for construction, $350,000 for design and $500,000 for easements and rights-of-way. The same document lists $130,000 secured as of that plan, and the 2025 state chart adds $550,000 for construction. Those figures help with a few practical questions:
The meeting link comes through ECIA's website and e-blast, and the county's project contact is listed above. The county plans to build the paved path along the 1.15 miles between Avenida Vista Grande and Encantado in the first half of 2027.
At Bunny Terry, we follow Eldorado's trails, greenbelts and county projects because they shape everyday life there. If you'd like help understanding how a project like the Azul trail touches a street you love, reach out and start your Santa Fe story with us.
Stay up to date on the latest real estate trends
Moving to Santa Fe
November 6 to 8, 2026
Santa Fe Opera 2027
Moving to Santa Fe
What Buyers and Sellers Need to Know
Santa Fe Homes
Let's talk about what this means for you as a buyer or seller
Moving to Santa Fe
You don't have to become someone new to find your niche in Santa Fe
You'll find art everywhere in Santa Fe County
We are committed to making each transaction the least complicated and easiest one you’ve ever been involved in. In old school speak, we bring our best professionalism to each and every transaction. We maintain a strong work ethic and believe that the client/broker relationship is a partnership built on honesty, trust, confidentiality and mutual respect. Let’s get started on this journey to fulfill your Santa Fe Real Estate dream!